Completed Projects

# Client Details Problem Encountered by Client Solution Provided by Aapaavani Year of Installation
1 Karwar City Municipal Corporation, Karwar STP Existing STP not working properly. Aerated Lagoon technology was not meeting the discharge standards. Upgradation of existing STP by adopting Membrane Bio Reactor Technology (MBR). Minimum Civil modifications carried out. 2023
2 Hotel Udupi Gardens, Kasaragod STP Domestic Wastewater from Hotel. Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2023
3 Kukke Subramanya Temple, Subramanya SURV Inconsistency in the existing drainage network map and overflow issues Surveying of existing manholes, preparation manhole network map and preparation of project report including recommendation for rectification of the problems. 2023
4 Sri Sathya Sai Seva Samsthe at Alike STP Domestic Effluent from Hostel Complex Design, Supply, Installation and Commissioning of Sewage Treatment Plant with Membrane Bio Reactor Technology. 2022
5 Ruchi Soya, Baikampady, Mangalore STP Domestic Wastewater from Office/ Halls/ Kitchen Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2022
6 Dr. Vikram Shetty (Doctor’s Colony STP Domestic Wastewater from Housing Colony. Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2022
7 Ramdhan Laundries, Bangalore ETP Treated water from the existing ETP was not providing satisfactory output water quality as per guidelines. Upgradation of existing ETP by adopting Membrane Bio Reactor Technology (MBR) followed by Reverse Osmosis. 2022
8 Vaishnavi Sabhbhavana, Manipal STP Domestic Wastewater from Office/ Halls/ Kitchen Design, Supply, Installation and Commissioning of Sewage Treatment Plant with Sequential Batch Reactor (SBR) Technology. 2022
9 Suriya Sadashiva Rudra Temple, Ujire STP Domestic Wastewater from Office/ Halls / Kitchen Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2022
10 HKA Bawa and Sons, Mukka ETP Existing ETP not functioning due to poor design. Upgradation of existing ETP by adopting Membrane Bio Reactor Technology (MBR). Minimum Civil modifications carried out. 2022
11 Bawa Fish Meal and Co., Mukka ETP Existing ETP not functioning due to poor design. Upgradation of existing ETP by adopting Membrane Bio Reactor Technology (MBR). Minimum Civil modifications carried out. 2022
12 Karnataka Housing Board (BCM, Hostel), Manipal STP Domestic Effluent from Hostel Complex Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2021
13 Shankar Group of Companies, Puttur (Bindu) ETP Existing ETP not working properly and was undersized. Upgradation of existing ETP by adopting Membrane Bio Reactor Technology (MBR). Minimum Civil modifications carried out and increased plant capacity. 2021
14 Hotel Kashi Palace (Ocean Pearl), Ujire ETP Domestic Effluent from Hotel & Lodging Complex. Design, Supply, Installation and Commissioning of Sewage Treatment Plant with Membrane Bio Reactor Technology. 2021
15 Alike Sri Sathya Sai Seva Samsthe, Alike STP Domestic Effluent from Hostel Complex. Design, Supply, Installation and Commissioning of Sewage Treatment Plant with Membrane Bio Reactor Technology 2021
16 NEXA (Venkat Motors), Hassan ETP Wastewater from Vehicle washing and servicing Design, Supply, Installation and Commissioning of Treatment Plant incorporating Primary, Secondary and Tertiary treatment units 2021
17 Armor Kartons, Athrady, Udupi ETP Wastewater containing color from a carton manufacturing unit. Design, Supply, Installation and Commissioning of Treatment Plant incorporating Primary, Secondary and Tertiary treatment units 2019
18 Sri Siddivinayaka Residential School, Hattiangady, Udupi STP Domestic Effluent from Hostel Complex. Sewage Water treatment Plant incorporating Membrane Bio Reactor Technology (Container based) 2019
19 Blue Logic, Bangalore ETP  Wastewater from Commercial Laundry unit. Design, Supply, Installation and Commissioning of Treatment Plant incorporating Primary, Secondary and Tertiary treatment units 2018